For Immediate Release Thursday 18 July 2024
Authorised by Anthony O’Reilly
Authorised by Anthony O’Reilly
Community Update on Young Stormwater Trunk Main Project
At the September 2023 Ordinary Council Meeting, Council resolved to commence the investigation, design and costing for the Young Stormwater Drainage Line D3, which runs along Lynch Street into Marina Street and discharges into Burrangong Creek. This decision was made due to the need for infrastructure upgrades to enhance Young’s stormwater management, crucial for flood mitigation.
Following thorough planning and preparatory work, Council is pleased to update the community on the progress of the Young Stormwater Trunk Main project.
Currently, the project is advancing through essential stages of investigation, design, and costing. Significant milestones so far include comprehensive service location assessments (including potholing), geotechnical investigations, and the proposed concept design alignment of stormwater pipes. Additionally, a review of environmental factors has been drafted, pending final alignment confirmation.
However, progress has been impacted due to the identification of a telecommunications cable that runs parallel to the current stormwater infrastructure. This has required extensive coordination with stakeholders outside of Council and has extended the timeline by over 6 months.
Looking ahead, the project timeline and milestones are as follows:
- Structural pit and pipe design: scheduled for completion by July 2024
- Draft detailed design package: expected by September 2024
- Finalisation of review of environmental factors: expected by September 2024
- Cost benefit analysis and economic feasibility study: scheduled for October 2024
- Final design package and costing: expected by October 2024
Once the initial stage of the project is completed, tender documents will be prepared and released to market. A suitably qualified tenderer can then be selected to complete the construction of stormwater Drainage Line D3.
Council’s commitment to the Young Stormwater Trunk Main Project will help ensure the resilience and efficiency of our stormwater infrastructure. Council looks forward to advancing this project.
-Ends-
Media enquiries – Hilltops Council 1300 445 586